We have started the framing on lot W24
The footings are poured on lot W24.
Strawn and Associates just started the footings on lot W24
Sylvester & Co. was there earlier this morning installing the control points for the footings.
The septic system is installed and ready for inspection on lot W24.
We have started a new contract home for some customers in Chinquapin.
This will be our Hickory plan with many nice options. We are excited to see this project go up because it incorporates a style that we have not done in quite a while. This home will have the kitchen at the front of the home and a large vaulted dining and living room at the back. The kitchen will also have a light well that brings the daylight in through the two dormer windows.